Live data · NRC report Oct 30, 2026

Nuclear outage schedule 2026-27

Which US reactors are down for refueling now, which go next, and how long each outage usually runs. Know where the work will be before the outage starts.

In outage now
16
16 refueling · 0 other
Fleet capacity
83%
Average output, all units
Full power
76
of 94 operating units
Next 30 days
4
Refueling windows opening

Every unit, by status

96 units

  • Full power76
  • Reduced2
  • Refueling16
  • Unplanned0
  • Offline0
  • Restarting2

01 · Now

In outage now

Reactors currently offline for refueling or maintenance, how far through each outage they are, and when they're expected back online.

Reactors at zero power on the latest NRC report
UnitProgress
North Anna

Unit 2

Refueling

Day 55 of ~35

Started Sep 6, 2026

Past the usual length, 20 days over

Callaway

Refueling

Day 35 of ~55

Started Sep 26, 2026

Back ~Nov 20, 2026

Cooper

Refueling

Day 33 of ~36

Started Sep 28, 2026

Back ~Nov 3, 2026

Palo Verde

Unit 1

Refueling

Day 28 of ~36

Started Oct 3, 2026

Back ~Nov 8, 2026

Prairie Island

Unit 1

Refueling

Day 28 of ~26

Started Oct 3, 2026

Past the usual length, 2 days over

Robinson

Unit 2

Refueling

Day 28 of ~31

Started Oct 3, 2026

Back ~Nov 3, 2026

Sequoyah

Unit 2

Refueling

Day 28 of ~27

Started Oct 3, 2026

Back ~Oct 30, 2026

Salem

Unit 1

Refueling

Day 27 of ~40

Started Oct 4, 2026

Back ~Nov 13, 2026

Point Beach

Unit 1

Refueling

Day 21 of ~25

Started Oct 10, 2026

Back ~Nov 4, 2026

Diablo Canyon

Unit 1

Refueling

Day 20 of ~35

Started Oct 11, 2026

Back ~Nov 15, 2026

Millstone

Unit 3

Refueling

Day 19 of ~42

Started Oct 12, 2026

Back ~Nov 23, 2026

Peach Bottom

Unit 2

Refueling

Day 19 of ~16

Started Oct 12, 2026

Past the usual length, 3 days over

Waterford

Unit 3

Refueling

Day 14 of ~78

Started Oct 17, 2026

Back ~Jan 3, 2027

Comanche Peak

Unit 1

Refueling

Day 12 of ~29

Started Oct 19, 2026

Back ~Nov 17, 2026

Farley

Unit 2

Refueling

Day 12 of ~38

Started Oct 19, 2026

Back ~Nov 26, 2026

Dresden

Unit 3

Refueling

Day 5 of ~19

Started Oct 26, 2026

Back ~Nov 14, 2026

02 · Forecast

Starting in the next 90 days

Refueling outages forecast to start in the next three months, based on each unit's past refueling cycle. Forecasts are estimates, not operator schedules. How we forecast

Refueling forecasts inside 90 days
UnitWindowConfidence
Oconee

Unit 1

Due nowForecast
River Bend Station

Unit 1

Due nowForecast
Turkey Point

Unit 4

Due nowForecast
Watts Bar

Unit 2

Due nowForecast

03 · All units

Full schedule

The next refueling window for every operating unit. Look up a plant, or filter by season, state, or operator.

Season

96 of 96 units, soonest window first

Refueling forecast for every operating US reactor
Confidence
Oconee

Unit 1

Due nowForecastSouth CarolinaDuke EnergyOct 22, 202424 months
River Bend Station

Unit 1

Due nowForecastLouisianaEntergyFeb 11, 202519 months
Turkey Point

Unit 4

Due nowForecastFloridaNextEra EnergyMar 1, 202518 months
Watts Bar

Unit 2

Due nowForecastTennesseeTVAApr 12, 202518 months
Hatch

Unit 2

Jan 21 to Mar 4, 2027ForecastGeorgiaSouthern CompanyFeb 9, 202524 months
LaSalle

Unit 2

Jan 22 to Mar 5, 2027ForecastIllinoisConstellationFeb 10, 202524 months
Brunswick

Unit 2

Feb 3 to Mar 17, 2027ForecastNorth CarolinaDuke EnergyMar 1, 202524 months
Calvert Cliffs

Unit 2

Feb 8 to Mar 22, 2027ForecastMarylandConstellationFeb 24, 202524 months
Catawba

Unit 2

Feb 8 to Mar 22, 2027ForecastSouth CarolinaDuke EnergySep 3, 202518 months
Quad Cities

Unit 1

Feb 12 to Mar 26, 2027ForecastIllinoisConstellationMar 10, 202524 months
Browns Ferry

Unit 2

Nov 20, 2026 to Jun 26, 2027ForecastAlabamaTVAMar 5, 202524 months
Vogtle

Unit 4

Feb 16 to Mar 30, 2027ForecastGeorgiaSouthern CompanySep 7, 2025Default 18 months
North Anna

Unit 1

Feb 21 to Apr 4, 2027ForecastVirginiaDominion EnergySep 7, 202518 months
D.C. Cook

Unit 2

Feb 24 to Apr 7, 2027ForecastMichiganIndiana Michigan PowerSep 20, 202518 months
Nine Mile Point

Unit 1

Feb 26 to Apr 9, 2027ForecastNew YorkConstellationMar 17, 202524 months

Plant breakdown

All reactors

Each plant with its units' output on the latest report, grouped by status. Open a plant for its full outage history.

Restarting

2 plants

In outage

16 plants

Below full power

2 plants

  • Hatch

    Baxley, GASouthern Company

    Unit 2 reduced
    Unit 1 100%Unit 2 90%

    Average output 95% avg

    42 GA jobs
  • Oconee

    Seneca, SCDuke Energy

    Unit 1 reduced
    Unit 1 87%Unit 2 100%Unit 3 100%

    Average output 96% avg

    218 SC jobs

At full power

36 plants

Source: US Nuclear Regulatory Commission daily power reactor status report. NRC source ↗

05 · Questions

Outage season, length, and cycle

Median refueling length
32 days
Median time between refuelings
18 months
Start in spring or fall
99%

When is nuclear outage season?

Refueling starts cluster in spring and fall. Of 1387 refueling outages in this record, 1378 (99%) started in February through May or September through November.

How long does a refueling outage last?

The median completed refueling in the last five years lasted 32 days, across 265 outages. A length of 14 to 90 days is the range we treat as a normal refueling.

How often do reactors refuel?

Across units with at least two measured gaps, the median cycle is 18 months. The schedule uses each unit's own gaps, not this fleet median.

How are these dates forecast?

We add a unit's median refueling gap to its last refueling start, then place a window around that date. If the date has passed and the unit is not in an outage, the row says Due now for up to 90 days. The date is an estimate from NRC history. It is not a schedule published by the operator.

How this page is built

Methodology

NRC power reactor status ↗

Sources

Power figures come from the NRC daily reactor status report. We store one row per operating unit from 1999 through the report dated Oct 30, 2026. The reason text comes from the NRC's daily pages, which add a comment about 28 days after the power figure. Those comments cover the last five years.

Detection

An outage is a run of days at 0% power. A hole of up to 3 days with no report stays in the same outage. If the unit comes back below 30% for 3 days or fewer and then returns to 0%, that is still one outage.

Classification

Each outage gets a score from the signals below.

Outage classification score
SignalScore
A comment containing "refueling" in the 45 days before the start, or during the outageadds 3
A coastdown in the 30 days before the startadds 2
A gap of 15 to 26 months since the previous refuelingadds 2
A start in February through May, or September through Novemberadds 1
A length of 14 to 90 daysadds 1
A scram on the start date, or a comment that names a scram or a reactor tripsubtracts 3
A length under 10 dayssubtracts 2
  • A score of 4 or more is a refueling.
  • A maintenance comment without a refueling comment is maintenance.
  • A score of 0 or less under 14 days is unplanned.
  • Anything else stays offline: we do not have enough to name it.

Forecasts

For a unit that is not in a refueling outage, the next start is the last refueling start plus the median gap between its last five refueling starts. The window is that date, plus or minus the larger of 21 days and the spread of those gaps. With fewer than two gaps, we use 18 months. If that date is already past and the unit is still up, we show "Due now" for up to 90 days, then step forward by whole cycles. We do not show a forecast date that has already passed.

Confidence

Forecast is the cycle estimate. Coasting down means the unit is already losing power in the pattern that usually comes before a refueling. Once the outage has started, the unit leaves the forecast table and appears under in outage now.

Updates

We read the NRC file twice a day. The date on this page is the report date in that file.

Limits

The NRC describes the daily status report as unevaluated information. Nuclear Hustle is not the NRC and is not affiliated with any plant operator. A forecast is an estimate from past outages. It is not a date the operator has scheduled.