Nuclear Power Plant

Hatch

Baxley, GeorgiaSouthern Company2 reactors

Unit 2 reduced

95% average output

NRC 10/30/2026

Reactor Units

Unit 1

Hatch 1

100%

Unit 2

Hatch 2

90%

Outages

Unit 1

Full power

Last refueling

Feb 4, 2024 to Mar 18, 2024, 43 days

Next window

Jan 9, 2028 to Feb 20, 2028

24 month cycle · ~43 days · Forecast

Last outages for Unit 1
TypeStartedEndedDays
MaintenanceOct 11, 2026Oct 14, 20263
UnplannedApr 24, 2026Apr 28, 20264
OfflineJan 17, 2026Mar 1, 202643
MaintenanceJul 12, 2025Jul 15, 20253
MaintenanceSep 27, 2024Oct 3, 20246

Unit 2

Reduced

Last refueling

Feb 9, 2025 to Mar 15, 2025, 34 days

Next window

Jan 21, 2027 to Mar 4, 2027

24 month cycle · ~29 days · Forecast

Last outages for Unit 2
TypeStartedEndedDays
MaintenanceMay 11, 2026May 16, 20265
UnplannedSep 14, 2025Sep 18, 20254
OfflineMar 27, 2025Apr 1, 20255
RefuelingFeb 9, 2025Mar 15, 202534
UnplannedNov 2, 2023Nov 6, 20234