Nuclear Power Plant

North Anna

Mineral, VirginiaDominion Energy2 reactors

Unit 2 in refueling outage

50% average output

NRC 10/30/2026

Reactor Units

Unit 1

North Anna 1

100%

Unit 2

North Anna 2

0%

Outages

Unit 1

Full power

Last refueling

Sep 7, 2025 to Oct 19, 2025, 42 days

Next window

Feb 21, 2027 to Apr 4, 2027

18 month cycle · ~36 days · Forecast

Last outages for Unit 1
TypeStartedEndedDays
UnplannedOct 22, 2025Oct 25, 20253
RefuelingSep 7, 2025Oct 19, 202542
UnplannedMay 30, 2024Jun 1, 20242
RefuelingMar 3, 2024Apr 7, 202435
MaintenanceSep 25, 2023Sep 27, 20232

Unit 2

Refueling outage · Day 55 of ~35

Last refueling

Mar 2, 2025 to Apr 6, 2025, 35 days

Next window

In outage now

18 month cycle

Last outages for Unit 2
TypeStartedEndedDays
RefuelingSep 6, 2026Ongoing55
RefuelingMar 2, 2025Apr 6, 202535
UnplannedDec 19, 2023Dec 25, 20236
RefuelingSep 10, 2023Oct 14, 202334
MaintenanceAug 14, 2022Sep 18, 202235