Nuclear Power Plant
All units at full power
100% average output
NRC 10/30/2026
Reactor Units
Unit 1
Surry 1
100%
Unit 2
Surry 2
100%
Outages
Unit 1
Full power
Last refueling
Oct 12, 2025 to Dec 29, 2025, 78 days
Next window
Mar 28, 2027 to May 9, 2027
18 month cycle · ~58 days · Forecast
| Type | Started | Ended | Days |
|---|---|---|---|
| Refueling | Oct 12, 2025 | Dec 29, 2025 | 78 |
| Unplanned | Aug 7, 2025 | Aug 11, 2025 | 4 |
| Refueling | Apr 7, 2024 | Jun 4, 2024 | 58 |
| Refueling | Oct 30, 2022 | Dec 17, 2022 | 48 |
| Refueling | Apr 25, 2021 | Jun 1, 2021 | 37 |
Unit 2
Full power
Last refueling
Apr 12, 2026 to Jun 8, 2026, 57 days
Next window
Sep 16, 2027 to Oct 28, 2027
18 month cycle · ~46 days · Forecast
| Type | Started | Ended | Days |
|---|---|---|---|
| Refueling | Apr 12, 2026 | Jun 8, 2026 | 57 |
| Refueling | Oct 27, 2024 | Dec 7, 2024 | 41 |
| Unplanned | Jun 10, 2023 | Jun 15, 2023 | 5 |
| Refueling | Apr 23, 2023 | Jun 8, 2023 | 46 |
| Refueling | Oct 24, 2021 | Dec 3, 2021 | 40 |
Open Roles at Dominion Energy
Virginia jobs →Dominion EnergyWATERFORD, CT
Dominion EnergyGLEN ALLEN, VA
Dominion EnergyWATERFORD, CT
Dominion EnergySURRY, VA
Dominion EnergyGLEN ALLEN, VA
Dominion EnergyWATERFORD, CT
Dominion EnergyFREEMAN, VA
Dominion EnergyGLEN ALLEN, VA
Dominion EnergyGLEN ALLEN, VA
Dominion EnergySURRY, VA
Dominion EnergyWATERFORD, CT
Dominion EnergyRICHMOND, VA
Analytics
We count visits with Clicky after you allow it. Sign-in cookies are set either way. You can change this on the privacy policy.