Nuclear Power Plant

Surry

Surry, VirginiaDominion Energy2 reactors

All units at full power

100% average output

NRC 10/30/2026

Reactor Units

Unit 1

Surry 1

100%

Unit 2

Surry 2

100%

Outages

Unit 1

Full power

Last refueling

Oct 12, 2025 to Dec 29, 2025, 78 days

Next window

Mar 28, 2027 to May 9, 2027

18 month cycle · ~58 days · Forecast

Last outages for Unit 1
TypeStartedEndedDays
RefuelingOct 12, 2025Dec 29, 202578
UnplannedAug 7, 2025Aug 11, 20254
RefuelingApr 7, 2024Jun 4, 202458
RefuelingOct 30, 2022Dec 17, 202248
RefuelingApr 25, 2021Jun 1, 202137

Unit 2

Full power

Last refueling

Apr 12, 2026 to Jun 8, 2026, 57 days

Next window

Sep 16, 2027 to Oct 28, 2027

18 month cycle · ~46 days · Forecast

Last outages for Unit 2
TypeStartedEndedDays
RefuelingApr 12, 2026Jun 8, 202657
RefuelingOct 27, 2024Dec 7, 202441
UnplannedJun 10, 2023Jun 15, 20235
RefuelingApr 23, 2023Jun 8, 202346
RefuelingOct 24, 2021Dec 3, 202140

Open Roles at Dominion Energy