Nuclear Power Plant

V.C. Summer

Jenkinsville, South CarolinaDominion Energy1 reactor

Full power

100% average output

NRC 10/30/2026

Reactor Units

Summer

Summer

100%

Outages

V.C. Summer

Full power

Last refueling

Feb 28, 2026 to Apr 10, 2026, 41 days

Next window

May 25, 2027 to Aug 3, 2027

16 month cycle · ~41 days · Forecast

Last outages for V.C. Summer
TypeStartedEndedDays
RefuelingFeb 28, 2026Apr 10, 202641
UnplannedJan 31, 2026Feb 8, 20268
UnplannedOct 15, 2025Oct 25, 202510
MaintenanceOct 4, 2025Oct 9, 20255
UnplannedFeb 11, 2025Feb 12, 20251