Nuclear Power Plant

Salem

Salem, New JerseyPSEG2 reactors

Unit 1 in refueling outage

50% average output

NRC 10/30/2026

Reactor Units

Unit 1

Salem 1

0%

Unit 2

Salem 2

100%

Outages

Unit 1

Refueling outage · Day 27 of ~40

Last refueling

Apr 13, 2025 to May 31, 2025, 48 days

Next window

In outage now

18 month cycle

Last outages for Unit 1
TypeStartedEndedDays
RefuelingOct 4, 2026Ongoing27
RefuelingApr 13, 2025May 31, 202548
UnplannedJan 17, 2025Jan 19, 20252
RefuelingOct 8, 2023Nov 12, 202335
RefuelingApr 9, 2022May 19, 202240

Unit 2

Full power

Last refueling

Apr 5, 2026 to May 7, 2026, 32 days

Next window

Sep 12, 2027 to Oct 24, 2027

18 month cycle · ~32 days · Forecast

Last outages for Unit 2
TypeStartedEndedDays
RefuelingApr 5, 2026May 7, 202632
RefuelingOct 6, 2024Nov 25, 202450
RefuelingApr 1, 2023Apr 28, 202327
UnplannedDec 24, 2022Dec 25, 20221
RefuelingOct 2, 2021Nov 12, 202141

Open Roles at PSEG

New Jersey jobs →