Nuclear Power Plant
In refueling outage
0% average output
NRC 10/30/2026
Reactor Units
Cooper
Cooper
0%
Outages
Cooper
Refueling outage · Day 33 of ~36
Last refueling
Sep 29, 2024 to Nov 4, 2024, 36 days
Next window
In outage now
24 month cycle
| Type | Started | Ended | Days |
|---|---|---|---|
| Refueling | Sep 28, 2026 | Ongoing | 33 |
| Refueling | Sep 29, 2024 | Nov 4, 2024 | 36 |
| Unplanned | Dec 17, 2022 | Dec 20, 2022 | 3 |
| Refueling | Oct 2, 2022 | Nov 14, 2022 | 43 |
| Offline | Nov 2, 2020 | Nov 4, 2020 | 2 |
Open Roles at NPPD
Nebraska jobs →Nebraska Public Power DistrictBrownville, NE
Nebraska Public Power DistrictBrownville, NE
Nebraska Public Power DistrictColumb, NE, US, 68602-0499 +1 more…
Nebraska Public Power DistrictColumb, NE, US
Nebraska Public Power DistrictNorfolk, NE
Nebraska Public Power DistrictBrownville, NE
Nebraska Public Power DistrictBrownville, NE
Nebraska Public Power DistrictColumb, NE, US
Nebraska Public Power DistrictBrownville, NE
Analytics
We count visits with Clicky after you allow it. Sign-in cookies are set either way. You can change this on the privacy policy.