Outage schedule/All Plants/Nine Mile Point

Nuclear Power Plant

Nine Mile Point

Scriba, New YorkConstellation2 reactors

All units at full power

100% average output

NRC 10/30/2026

Reactor Units

Unit 1

Nine Mile Point 1

100%

Unit 2

Nine Mile Point 2

100%

Outages

Unit 1

Full power

Last refueling

Mar 17, 2025 to Apr 5, 2025, 19 days

Next window

Feb 26, 2027 to Apr 9, 2027

24 month cycle · ~19 days · Forecast

Last outages for Unit 1
TypeStartedEndedDays
RefuelingMar 17, 2025Apr 5, 202519
RefuelingMar 13, 2023Apr 20, 202338
RefuelingMar 22, 2021Apr 10, 202119
OfflineApr 30, 2019May 6, 20196
RefuelingMar 18, 2019Apr 27, 201940

Unit 2

Full power

Last refueling

Mar 9, 2026 to Apr 2, 2026, 24 days

Next window

Feb 16, 2028 to Mar 29, 2028

24 month cycle · ~23 days · Forecast

Last outages for Unit 2
TypeStartedEndedDays
RefuelingMar 9, 2026Apr 2, 202624
UnplannedSep 24, 2024Sep 28, 20244
RefuelingMar 4, 2024Mar 27, 202423
UnplannedSep 3, 2023Sep 7, 20234
MaintenanceSep 5, 2022Sep 14, 20229

Open Roles at Constellation

New York jobs →