Nuclear Power Plant
Davis-Besse
Oak Harbor, OhioFirstEnergy1 reactor
Full power
100% average output
NRC 10/30/2026
Reactor Units
Davis-Besse
Davis-Besse
100%
Outages
Davis-Besse
Full power
Last refueling
Mar 1, 2026 to Mar 31, 2026, 30 days
Next window
Feb 7, 2028 to Mar 20, 2028
24 month cycle · ~30 days · Forecast
| Type | Started | Ended | Days |
|---|---|---|---|
| Maintenance | Sep 8, 2026 | Sep 19, 2026 | 11 |
| Refueling | Mar 1, 2026 | Mar 31, 2026 | 30 |
| Unplanned | Aug 13, 2025 | Aug 19, 2025 | 6 |
| Refueling | Mar 3, 2024 | Mar 29, 2024 | 26 |
| Maintenance | Dec 5, 2022 | Dec 18, 2022 | 13 |