Nuclear Power Plant

D.C. Cook

Bridgman, MichiganIndiana Michigan Power2 reactors

All units at full power

100% average output

NRC 10/30/2026

Reactor Units

Unit 1

D.C. Cook 1

100%

Unit 2

D.C. Cook 2

100%

Outages

Unit 1

Full power

Last refueling

Sep 19, 2026 to Oct 22, 2026, 33 days

Next window

Mar 4, 2028 to Apr 15, 2028

18 month cycle · ~33 days · Forecast

Last outages for Unit 1
TypeStartedEndedDays
RefuelingSep 19, 2026Oct 22, 202633
RefuelingMar 22, 2025Apr 30, 202539
RefuelingOct 14, 2023Nov 14, 202331
UnplannedAug 29, 2022Sep 5, 20227
RefuelingApr 2, 2022May 30, 202258

Unit 2

Full power

Last refueling

Sep 20, 2025 to Oct 25, 2025, 35 days

Next window

Feb 24, 2027 to Apr 7, 2027

18 month cycle · ~42 days · Forecast

Last outages for Unit 2
TypeStartedEndedDays
UnplannedJan 18, 2026Jan 21, 20263
RefuelingSep 20, 2025Oct 25, 202535
MaintenanceJun 28, 2024Jul 2, 20244
OfflineMay 16, 2024May 17, 20241
RefuelingMar 23, 2024May 4, 202442