Outage schedule/All Plants/Crane Clean Energy Center

Nuclear Power Plant

Crane Clean Energy Center

Middletown, PennsylvaniaConstellation1 reactor

Restarting

0% average output

NRC 10/30/2026

Reactor Units

Unit 1

Three Mile Island 1

0%

This plant is returning to commercial operation and may not appear in the current NRC operating feed.

Outages

Unit 1

Restarting

Last refueling

Sep 21, 2019 to Mar 23, 2021, 549 days

Next window

Sep 6, 2027 to Oct 18, 2027

24 month cycle · ~26 days · Forecast

Last outages for Unit 1
TypeStartedEndedDays
RefuelingSep 21, 2019Mar 23, 2021549
OfflineOct 11, 2017Oct 12, 20171
RefuelingSep 19, 2017Oct 8, 201719
UnplannedDec 1, 2016Dec 12, 201611
RefuelingOct 30, 2015Nov 25, 201526